The quartz top finally arrived today. Here are some pictures:
Thursday, November 29, 2007
Tuesday, November 13, 2007
Walkthrough, etc.
We did the walkthrough on Monday and everything looked good. There were a few things that needed to be addressed, but they were all minor.
We get the keys tomorrow and start the moving process. We will likely sleep there Friday night.
We get the keys tomorrow and start the moving process. We will likely sleep there Friday night.
Friday, November 9, 2007
Not Much
We went over yesterday and they hadn't really done much. The painter finished the little things, and I think they capped off the central vac ports. They still have a lot to do: insulate and put vapour barrier on the entire basement, rough in the central vac to the garage, clean the entire place, install the microwave, fix the issue with the hole in the cold cellar being too close to the gas meter (less than 3 feet - duh, parging on the foundation, place all the vents, and probably a few other things that we haven't noticed.
Tuesday, November 6, 2007
Almost ready
Friday, November 2, 2007
Electrician was in today
Thursday, November 1, 2007
No pictures (forgot the camera today) but...
The plumber was in today and installed all the toilets, sinks and fixtures, and the water's on. The siding is done and the gas roughins are complete (range and dryer). I didn't notice the one for the bbq, but I did see the cutoff in the basement for it.
We noticed that he was putting the pillars in the wrong place. Apparently he wasn't told that we wanted one less pillar, so he was going by the original plan. Good thing I was there to tell him otherwise. Sheesh.